At Collaroy Plateau Public School, we completed essential civil works to improve drainage and site safety. The project involved replacing approximately 60 metres of kerb and gutter, with 30 metres constructed at a higher 400mm profile to function as a retaining wall. Works also included the installation of a 250mm stormwater pipe linking two pits, replacement of the lintel above the lower pit, and the integration of an agline with aggregate backfill for improved subsurface drainage. The kerb and gutter were poured as one continuous structure, ensuring strength, durability, and long-term performance.
Industry
Education
Location
Collaroy Plateau
Year
2022
Client
Collaroy Plateau Public School
Service
Construction, Ground Works